Groningen homeowners still waiting too long for home insulation plans
Groningen homeowners are waiting longer for home insulation plans under the Nij Begun programme than the government wants, as efforts to cut waiting times have not worked well enough, it says.

i
Illustrative photo: Jolanda66 / Pixabay Content LicenseMeasures to cut the wait for home insulation plans (isolatieplannen) in Groningen have so far had too little effect, Housing Minister Boekholt-O'Sullivan has told the Tweede Kamer. In written answers received on 27 October, also sent on behalf of the interior minister, she said the national government and the region found it very unfortunate that people were waiting longer than desired under Nij Begun.
Why it matters
- A system is being set up to deal with urgent cases first. These include households in energy poverty, owners renovating while buying or selling a home, and people with serious structural problems such as leaks.
- Homeowners can already make a start on measures costing up to €10,000 without an insulation plan. The government is encouraging this route until steps to speed up the plans have a noticeable effect.
The government wants to guarantee that every plan is complete, accurate and ready for the owner to act on, the minister said. Owners will be investing heavily in their homes on the strength of these plans. "They must be able to trust that the plans are properly drawn up and correct," she said.
The government said back on 21 April that it wanted to shorten processing times. Steps to clear the backlog include making the quality team four times larger, and it will grow further. Further agreements with insulation advisers aim to get more plans approved first time, so that fewer checks are needed.
Better plans are crucial to preventing further delays, the minister said. Talks about quality have been held with all agencies and advisers, and the compulsory training for advisers is being critically reviewed. Those who have already been trained were offered practical training days this autumn.
Agencies that repeatedly submit plans falling short of the requirements are given a warning. If the shortcomings persist, they can be barred from further work. This does not apply to minor changes that can be made quickly.
The government is also looking at whether the insulation plan can be simplified without compromising the programme's goals. It will take into account the results of an evaluation of the approach that is now under way.
Source: Tweede Kamer