TenneT to upgrade 800 km of power lines, expects up to 30% more capacity
Grid operator TenneT will replace cables on existing overhead lines, starting next spring near Breukelen, to ease pressure on an overloaded electricity grid.

i
Illustrative photo: Busspotter / CC BY-SA 4.0TenneT is to upgrade about 800 kilometres of its existing overhead high-voltage lines. By replacing the cables between the pylons with new conductors, the grid operator expects to transport up to 30 percent more electricity over those lines.
The extra capacity is meant for households and businesses, and for the growing amount of electricity from wind and solar farms. The work is a response to the overloaded grid.
Work on the high-voltage connections between Breukelen and Kortrijk begins next spring. Work is also planned near Krimpen aan den IJssel and Diemen, with connections near Beverwijk and Oostzaan to follow. In Overijssel, TenneT has already started upgrading the connection between Harculo, Raalte and Nijverdal.
TenneT plans to largely keep using the existing pylons and routes, so no extra space is needed for new high-voltage connections. During the work it also carries out maintenance: insulators and earth wires are replaced where needed, and parts of pylons and foundations are repaired.
Demand is rising because households use more electricity for heating and transport, and businesses are switching to power. "The capacity of the grid must at least double to meet the fast-growing demand for electricity from households and businesses," TenneT says.
Source: CBS
More on energy and the grid · business and companies