The Netherlands, explained in English · Thursday 19 November 2026Thu 19 Nov

Society

No trains between Den Helder and Heerhugowaard until 20 November

NS is running replacement buses in North Holland while track work continues, after crowded buses and long waits at the start of the week.

NS Sprinter train in the countryside near Hoorn
iIllustrative photo: Rob Dammers / CC BY 4.0

No trains are running between Den Helder and Heerhugowaard from Saturday 14 November to Friday 20 November, as NS carries out the second phase of its track work in the north of North Holland. Replacement buses cover the route.

Why it matters

  • No trains ran between Heerhugowaard and Hoorn or between Heerhugowaard and Alkmaar up to and including Friday 13 November.
  • From Saturday 14 to Friday 20 November, no trains will run between Den Helder and Heerhugowaard.
  • Passengers on these routes face longer journeys on replacement buses.

The replacement buses were very crowded at the start of the week. On Monday there were long waits in Schagen.

After complaints, NS put extra buses on the road in the following days. "We've tweaked things and it now seems to be going well," an NS spokesperson said.

The spokesperson said the first day of works is always a matter of finding your way. "We try to inform travellers as well as possible, but it involves a large stretch of track. It is a huge operation," he said.

The work is split into three phases. After 20 November, final work and testing will take place.

See more of NLnow in Google: add it as a preferred source