EU deal scraps nitrogen test for power grid expansion
EU member states and the European Parliament agreed faster permitting for energy projects on Tuesday night. The deal removes a nitrogen rule that often stalls grid reinforcement in the Netherlands.

i
Illustrative photo: Busspotter / CC BY-SA 4.0Expansions of the electricity grid will no longer need the mandatory nitrogen test, under a deal on faster permitting for energy projects. Negotiators for EU member states and the European Parliament settled the Grids Package on Tuesday night.
Dutch grid operators want to reinforce the grid to connect new homes and businesses, but often get stuck on nitrogen rules. The new exemption is meant to remove that obstacle. A survey by the Nederlandse Vereniging Duurzame Energie (NVDE), the renewable energy association, found last year that nitrogen rules delay or halt many thousands of energy projects.
“Really good, because the logic holds, area by area off the lock. Nice that we can build on the work of the BBB.”
From now on, member states must ensure that the rapid construction of electricity infrastructure is not hindered "in any way" by the temporary emissions that building it causes. Under certain conditions, the exemption will also cover energy storage, charging stations, small solar installations and hydrogen infrastructure.
“Yesterday there were late-night negotiations in Brussels on nitrogen exemptions for the electricity grid, hydrogen, energy storage and charging infrastructure. Great that this succeeded, also thanks to the efforts of the VVD! Important in the approach to grid congestion.”
The package also sets shorter deadlines for authorities to approve permit applications: three to six months for grid connections, three months for solar, six months for energy storage and charging stations, and two years for hydropower storage.
The European Commission's original proposal would have approved applications tacitly once a deadline passed. Member states resisted this, and may now decide for themselves whether to apply tacit approval.
Renewable energy, the grid, energy storage and charging stations will automatically count as being of overriding public interest.
The deal will be put to the full Parliament and all 27 member states. Once they confirm it, member states will have one and a half years to write the rules into national law.
More on energy and the grid · the world with a dutch angle · climate, nature and farming