# Grid connection queue expected to halve by end-2028

> State Secretary Jo-Annes de Bat told MPs he expects the grid connection queue, which is also holding back housebuilding, to be halved by the end of 2028.

Economy · published 2026-11-26 05:33 · https://nlnow.nl/a/grid-waiting-list-expected-to-halve-by-end-2028/

The queue for connections to the Dutch electricity grid will be half its size by the end of 2028, De Bat, the state secretary for climate and green growth, said on Wednesday during a committee debate in the Tweede Kamer, the House of Representatives.

At stake are plans by more than 15,000 businesses to expand or become more sustainable. The threat of grid overload means they cannot currently get the new or bigger connection they are waiting for. The squeeze is slowing housebuilding too.

> From today's debate: in December the grid operators will come with new congestion studies with adjusted forecasts. The study from this article will be included in that. Hopefully it opens the door to more connections.
> — Alisha Müller, VVD MP, on X (https://x.com/AlishaMuller/status/2125614838353420435) (translated from Dutch)

Location will still matter. Congestion arises locally and is usually solved locally too, De Bat cautioned, pointing to large differences across the country. Even after 2030, businesses in some places will face a long wait to be connected.

There may be room for more connections than assumed. This week the consultancy Sirm concluded that the grid is less full than thought in 40% to 60% of areas, as demand for electricity is growing more slowly than expected. De Bat also expects good news at the end of this year, when grid operators are due to publish new studies mapping congestion.

To shorten the queue, he is counting on a package of measures, a bigger grid and, in particular, smarter use of it. Because the network is not full all the time, companies that can shift their consumption away from peak hours can often get space. Few do so at present, but De Bat said he expects grid operators to launch products next year that make such flexibility more attractive.

Grid connection requests for housing are another target. De Bat argued that the hundreds of thousands of homes planned for the coming years will never all be started in that period. A careful sift of the waiting lists would therefore take some requests out, without putting building ambitions at risk.

## Background

- **Tweede Kamer**: The House of Representatives, the lower and more powerful house of the Dutch parliament. Its 150 members are elected directly; it can amend bills and holds the cabinet to account.
- **staatssecretaris**: A state secretary is a junior minister in the Dutch government who leads a specific policy area within a ministry without being a full minister. In the Netherlands, a state secretary is responsible for a defined portfolio, such as climate and green growth, and reports to Parliament on that work.
- **netbeheerders**: Netbeheerders (grid operators) are the companies that own and manage the Dutch electricity and gas networks. TenneT runs the high-voltage transmission grid, and regional companies run the local distribution networks that connect homes and businesses. Their network capacity and tariffs are overseen by the regulator ACM.